NEXT PROJECT

Hartford Ave. & Wrentham Road WTP Improvements – Bellingham, Ma

Modifications to existing Hartford Ave. Water Treatment Plant to increase its flow capacity for iron and manganese removal to 2.40 MGD by combining the DPW existing Well No. 5 and Well No. 12 with the currently treated Well No. 7 and No. 8. The project includes submersible well pumps, well redevelopment, two new GreensandPlus filters, upgraded filter control valves, a clearwell baffle system, chemical feed systems, ancillary equipment and controls.

Also included in this project is the construction of a new 2.41 MGD water treatment plant at Wrentham Road for iron and manganese removal from several DPW existing wells. This project includes submersible well pumps, well redevelopment, a GreensandPlus filtration system, a clearwell, chemical feed systems, a wash water recycling system, settled solids waste system, ancillary equipment and controls.